Met an error during Oracle database 19c software installation on AIX 7.2 like this:

PRVE-10167 : I/O Completion Ports (IOCP) device status did not match the required value on node "NodeName". [Expected = "Available"; Found = "Defined"]

The error message told us that the status needs to be "Available" instead of "Defined" for IOCP state. Let's check the current setting of IOCP.

# lsdev -c iocp
iocp0 Defined  I/O Completion Ports

Solution

We can use smitty to change the status.

# smitty iocp
  Change / Show Characteristics of I/O Completion Ports
STATE to be configured at system restart            available

Let's check the current setting again.

# lsdev -c iocp
iocp0 Available  I/O Completion Port

We need to reboot the system to bring it effect.

# reboot
Rebooting . . .

If necessary, we mount all file systems back after system started.

# mount -a